Progress of work: End of Day 10

The work is going on in full swing in the school ground of Tulatoli Primary School, Narsingdi, Bangladesh. Its wonderful to see that the process is already having an impact on children and adults in various ways. The children who visit the site in different times are engaged with different activities using different loose parts (outcome of construction work, construction materials). They are already using the small hills (we are planning to plant grass to make it grassy hills in the adventure play area). They climb up and down the hills, used a small piece of wood to make bridge. They are making fountains using water and sand. They are also helping in the construction work in many ways- bringing bricks to the place of construction, working to give a shape to the grassy hill and helping in local plants search etc. Here are some photos...


 House/Shelter/Learning in Groups

Outdoor Classroom/ Gathering area


Mound/ Grassy Hills

Children making fountains

Comments

Post a Comment

Popular posts from this blog

We got our Experimental School

Its Tulatuli Primary School After a rigorous (I will surely call it rigorous considering all the aspects we considered) selection process finally we all (me, Simon, Sarah and Eva) are unanimous about one school- Tulatuli Primary School. The reasons or the justifications for the selection of this school is- 1)       Communication is easy from the place of the researcher and also from any point where we can have the construction materials we would like to use. This is important as we are going to work here for a longer period of time. 2)       The school is typical of most of the primary schools in all its aspects- the number of teachers and students, the physical condition and design of the school buildings and also the size of the school ground. 3)       The teachers seem enthusiastic. The Headmaster is a young energetic person and I hope that he can motivate his co-teachers in this project.  The Headmaster seemed inspired by my previous works and achievements which might hel

Progress of Work: Day 28

We are almost at the last phase of our construction. Masonry work is finished, bamboo work is a little bit slow and still going on. We have planted plants and the water plants are in site too. Here are some pictures taken today on Day 28. Figure 01: Outdoor Classroom  Figure 02: Lerning with loose parts Figure 03: Shelter/ Learning in groups Figure 04: Natural Learning area (We could only plant some plants but this not the planting season. They will grow during the rains) Figure 05: Garden/ Growing area Figure 06: Water learning area